Introduction to the GANTT diagram

The GANTT diagram is a tool that allows the user to model the planning of tasks necessary to the performance of a project. This tool was invented in 1917 by Henry L. Gantt.

Given the relative ease of reading of GANTT diagrams, this tool is used by almost all project managers in all sectors. The GANTT diagram is a tool for the project manager, which allows for the graphic representation of the progress of the project, but it is also a good means of communication amongst the various persons involved in a project.

This type of modeling is particularly ease to implement with a simple spreadsheet, but there are also specialized tools, the best-known being Microsoft Project. There are also free equivalents of this type of software.

Creating a GANTT diagram

In a GANTT diagram, each task is represented by a line, while the columns represent the days, weeks, or months of the schedule depending on the duration of the project. The estimated time for a task is modeled by a horizontal bar, the left end of which is positioned on the intended start date and the right end of which is on the intended end date. Tasks can be placed in sequential chains or carried out simultaneously.

GANTT diagram of a Web project

If tasks are sequential, priorities can be modeled using an arrow from the upstream task to the downstream task. The downstream task cannot be carried out until the upstream task has been completed.

Priorities in a GANTT diagram

As a task progresses, the bar that represents it is filled proportionallz to its degree of completion. Thus, it is possible to get a quick overview of the progress of the project bz tracing a vertical line across the tasks at the level of the current date. The completed tasks are located to the left of this line; tasks that have not yet begun are at the right, while the tasks being carried out are crossed by the line. If there filling is located to the left of the line,the task is in delay compared to the plan!

Ideally, such a diagram should not have more than 15 or 20 tasks so that it can fit on a single A4 page. If the number of tasks is greater, it is possible to create additional diagrams detailing the planning of the main tasks.

Milestones

Additionally, it is possible to have the major events other than the tasks themselves show on the plan as points of connection for the project: these are the milestones.

The milestones allow the project to be decided in clearly identifiable phases, which avoids the end of the project being too far off (this is often referred to as the "tunnel effect", a project with a long duration and no intermediate endpoint). A milestone could be the production of a document, the holding of a meeting, or a deliverable of the project. The milestones are tasks of zero duration, represented on the diagram by a specific symbol, most frequently a reverse triangle or a diamond.

Representation of a milestone in a GANTT diagram

Resources

It is generally possible (and useful) to show resources, human or material, on the diagram, in order to allow for estimation of needs and give an idea of global cost.

For the sake of concision, the initials or the names of those responsible for each task will sometimes suffice.

Tools



Last update on Thursday October 16, 2008 02:43:19 PM.This document entitled « GANTT diagram » from Kioskea (en.kioskea.net) is made available under the Creative Commons license. You can copy, modify copies of this page, under the conditions stipulated by the licence, as this note appears clearly.
Best answers for « GANTT diagram » in :
Download GANTT Project Show GanttProject is a free project management tool allowing to realize GANTT diagrams to plan a project and manage the resources. GanttProject is a complete tool proposing import / export features towards Microsoft Project, as well as export functions...
Processor Show Introduction The processor (CPU, for Central Processing Unit) is the computer's brain. It allows the processing of numeric data, meaning information entered in binary form, and the execution of instructions stored in memory. The first...
Free alternative to Microsoft Project ShowFree alternative to Microsoft Project Microsoft Project is a software project management highly valued for managing large projects, to achieve the (Gantt chart or PERT network) There is no free software as comprehensive as Microsoft...
[FreeMind] Post a mindmap in a web page Show[FreeMind] Post a mindmap in webpage Flash Java Applet A mind map is a diagram that can used to represent words, ideas, tasks, relatate to a specific theme.These can be very useful to describe various procedures or data flow with a...
Download O-Schema ShowDescription: O-Schema is a generator diagram (ERD) for Oracle databases. Features: Apart from creating charts and diagrams, it also allows you to create and edit tables and relationships between data. Advantages: The diagrams can be saved as...
Networking - 3-Tier Client/Server Architecture ShowIntroduction to 2-Tier Architecture 2-tier architecture is used to describe client/server systems where the client requests resources and the server responds directly to the request, using its own resources. This means that the server does not...
VGA (SUB-D15) connector ShowSUB-D15 plugs Mini Sub-D (ou SUB-D15) is a 15-pin connector (with three rows of 5 pins each). This kind of connector is built into most graphics cards and is used to send 3 analog signals to the monitor, which correspond to the red, blue, and green...